So, everything is connected with each other. And of course we need the money to hire people for our store. a bank loan) without having a business license. There are also some dependencies between the tasks.įor example, we can’t get a bank account without having a business license. If you look at the list, you notice that the tasks must be performed in a specific order. In this project, we need to accomplish the following tasks: You can see now the start date for our tasks is 14th September 2020. Press OK after you’ve entered the project start date. For this example, we want to base our schedule on a start date of 14th September 2020.
If you already have committed to a golive date and want to know by when you need to begin work, then chose Schedule from Project End Date to trigger the backward planning. Note: You can decide whether you want Microsoft Project to schedule your project forward from a specific start date or backward from a desired end date.